Multiple Choice
During the year,Paul Company used a predetermined overhead rate of $3.50 per direct labour hour,based on an estimate of 22,000 direct labour hours to be worked during the year.Actual overhead cost and activity during the year were:
What was the under- or overapplied overhead for the year?
A) $2,500 overapplied.
B) $2,500 underapplied.
C) $10,500 overapplied.
D) $13,000 underapplied.
Correct Answer:

Verified
Correct Answer:
Verified