Y Company reported the following actual costs data for the year:
Y Company used a predetermined overhead rate based on direct labour hours.Estimated annual manufacturing overhead cost and direct labour hours were $150,000 and 20,000,respectively.
Required:
a.What was the pre-determined manufacturing overhead rate?
b.Calculate the cost of goods manufactured.
c.What was the cost of goods sold before adjusting for any under or overapplied overhead?
d.By how much was manufacturing overhead cost under or overapplied?
e.Prepare a summary journal entry to close any under or overapplied manufacturing overhead cost to cost of goods sold.Is such an entry appropriate in this situation? Why or why not?
f.Analyze the under or overapplied manufacturing overhead costs calculated in part c above into two separate components: amount due to incorrect estimate of the annual manufacturing overhead costs and an amount due to incorrect estimate of the annual direct labour cost.
Correct Answer:

Verified
a.Predtermined manufacturing overhead ra...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q12: Dowan Company uses a predetermined overhead rate
Q13: Dotsero Technology,Inc.,has a job-order costing system.The
Q14: The Milo Company's records for May
Q15: A public accounting firm would have cost
Q16: Simplex Company has the following estimated
Q18: When a job is completed and transferred
Q19: The predetermined overhead rate is computed by
Q20: Summit Company has provided the following
Q21: Sai Company uses a job order
Q108: The most common accounting treatment of underapplied