ABC Company's Total Overhead Costs at Various Levels of Activity

Question 52

Essay

ABC Company's total overhead costs at various levels of activity are presented below:
 Machine hours  Total overhead costs  March 60,000$216,800 April 50,000194,000 May 70,000239,600 June 80,000262,400\begin{array}{|l|r|r|}\hline & \text { Machine hours } & \text { Total overhead costs } \\\hline \text { March } & 60,000 & \$ 216,800 \\\hline \text { April } & 50,000 & 194,000 \\\hline \text { May } & 70,000 & 239,600 \\\hline \text { June } & 80,000 & 262,400 \\\hline\end{array}
Assume that the overhead costs above consist of utilities,supervisory salaries,and maintenance.At the 50,000-machine-hour level of activity,these costs are presented below:
 Utilities (V) $54,000 Supervisory salaries (F) 62,000 Maintenance (M) 78,000 Total overhead costs $194,000\begin{array}{|l|r|}\hline \text { Utilities (V) } & \$ 54,000 \\\hline \text { Supervisory salaries (F) } & 62,000 \\\hline \text { Maintenance (M) } & 78,000 \\\hline \text { Total overhead costs } & \$ 194,000 \\\hline\end{array}
V = Variable,F = Fixed,M = Mixed
The company wants to break down the maintenance cost into its basic variable and fixed cost elements.
Required:
a)Estimate the maintenance cost for June.
b)Use the high-low method to estimate the cost formula for maintenance cost.
c)Estimate the total overhead cost at an activity level of 55,000 machine hours,using the separate estimates you obtained for its components.
d)Estimate the total overhead cost at an activity level of 55,000 machine hours,independent of the separate estimates you obtained for its components.

Correct Answer:

verifed

Verified

a)Maintenance cost for June:
blured image b)High-lo...