Multiple Choice
Unfavorable activity level variances are due to ________.
A) planned costs exceeding actual costs
B) actual costs exceeding planned costs
C) planned output exceeding actual output
D) actual output exceeding planned output
Correct Answer:

Verified
Correct Answer:
Verified