Stein Company planned to produce 12,000 units.This level of production required 20 setups at a cost of $18,000 plus $500 per setup.Actual production was 10,000 units,requiring 15 setups.Actual setup cost was $26,000.What is the flexible budget variance for setup costs?
A) $500 Favorable
B) $500 Unfavorable
C) $2,000 Favorable
D) $2,000 Unfavorable