The following information is available:
Actual output was 1,000 units.The company's per unit standards call for 15 yards of direct material at $10.00 per yard and 4 hours of direct labor at $9.50 per hour.The company purchased and used 11,000 yards of material.
Required:
A)Compute the price and quantity variances for direct material.
B)Compute the price and quantity variances for direct labor.
Correct Answer:

Verified
A)Price Variance = 11,000 x ($12 - $10)=...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q67: A quantity variance for direct materials measures
Q101: Black Company planned to produce and sell
Q102: A _ is most likely to be
Q104: The variable overhead efficiency variance depends on
Q105: Actual results may differ from the static
Q107: Currently attainable standards are levels of performance
Q109: The fixed overhead spending variance equals the
Q111: Ben Company planned to produce 12,000 units.This
Q129: Favorable variances do not require investigation.
Q135: A flexible budget is different from a