Multiple Choice
Costs that change abruptly at different levels of activity because the resources and their costs come in indivisible chunks are called ________.
A) mixed costs
B) variable costs
C) fixed costs
D) step costs
Correct Answer:

Verified
Correct Answer:
Verified