Multiple Choice
Joshua Lee, an engineer at Footprints Inc., is provided with a design by the creative team in his company for creating a software that would help travel agents answer and track traveler requests efficiently. He is now converting the design into an operational information system. Which of the following phases of the SDLC is the software currently in?
A) analysis phase
B) development phase
C) implementation phase
D) planning phase
Correct Answer:

Verified
Correct Answer:
Verified