To forecast total costs at a given level of production, management would use which of the following calculations?


A) Average cost × total units predicted
B) Total fixed cost × total units predicted
C) Total fixed cost + (variable cost per unit × total units predicted)
D) Total fixed cost + variable cost per unit

Correct Answer: