Solved

Job 222 Started on June 1 and Finished on July

Question 180

Multiple Choice

Job 222 started on June 1 and finished on July 15. Total cost on July 1 was $12,700, and the costs added in July were $188,800. The entry for the sale at a price of $310,500 would be:


A) Job 222 started on June 1 and finished on July 15. Total cost on July 1 was $12,700, and the costs added in July were $188,800. The entry for the sale at a price of $310,500 would be: A)    B)    C)    D)
B) Job 222 started on June 1 and finished on July 15. Total cost on July 1 was $12,700, and the costs added in July were $188,800. The entry for the sale at a price of $310,500 would be: A)    B)    C)    D)
C) Job 222 started on June 1 and finished on July 15. Total cost on July 1 was $12,700, and the costs added in July were $188,800. The entry for the sale at a price of $310,500 would be: A)    B)    C)    D)
D) Job 222 started on June 1 and finished on July 15. Total cost on July 1 was $12,700, and the costs added in July were $188,800. The entry for the sale at a price of $310,500 would be: A)    B)    C)    D)

Correct Answer:

verifed

Verified

Unlock this answer now