Multiple Choice
Gwynnie Pie Company makes dessert pies for national fast food chains. Gwynnie Pie Company is considering using ABC costing and has the following activity cost pools and information available: Gwynnie Pie Company currently uses a plantwide overhead rate based on total estimated machine hours of 100,000 hours.
The following information was gathered regarding Job 607:
# of units in the job = 5,000
# of units in each batch = 1,000
# of setups required to complete the job = 1
# of machine hours = 220
How much would the overhead be overcosted or undercosted if Gwynnie Pie Company continues to use the plantwide overhead rate as opposed to using ABC Costing?
A) $931.69 undercosted
B) $994.40 overcosted
C) $62.71 overcosted
D) $45.34 undercosted
Correct Answer:

Verified
Correct Answer:
Verified
Q82: Beartowne Enterprises uses an activity-based costing system
Q83: The lost profits from lost customers are
Q84: OP Technologies Manufacturing manufactures small parts and
Q85: If a company were to decrease its
Q86: Inspection is considered a non-value-added activity.
Q88: Cost distortion occurs when some products are
Q89: Indications that a product cost system needs
Q90: The Sit-N-Spin Corporation manufactures and assembles office
Q91: Which of the following items is not
Q92: The cost allocation rate for each activity