Multiple Choice
Which of the following causes the master budget variance between the amounts in the master budget and the flexible budget of a revenue center?
A) The cost of sales
B) The number of units sold differs from planned sales levels
C) The selling price per unit
D) Both the selling price and the number of units sold
Correct Answer:

Verified
Correct Answer:
Verified