Multiple Choice
Answer the following question(s) using the information below.Munoz Inc.produces a special line of plastic toy racing cars in batches.To manufacture a batch of the cars Munoz Inc.must setup the machines and molds.Setup costs are batch-level costs because they are associated with batches rather than individual units of products.A separate Setup Department is responsible for setting up machines and molds for different styles of car.Setup overhead costs consist of some costs that are variable and some costs that are fixed with respect to the number of setup hours.The following information pertains to June 2012:
-Calculate the efficiency variance for variable setup overhead costs.
A) $1,900 unfavourable
B) $600 favourable
C) $1,900 favourable
D) $600 unfavourable
E) $400 unfavourable
Correct Answer:

Verified
Correct Answer:
Verified
Q50: Answer the following question(s)using the information below.Munoz
Q51: Use the information below to answer the
Q52: A favourable variable manufacturing overhead efficiency variance
Q53: A fixed manufacturing overhead cost pool can
Q54: Answer the following question(s)using the information below.Munoz
Q56: Mostly Miniatures has just implemented a new
Q57: When machine-hours are used as an overhead
Q58: The variable overhead flexible-budget variance can be
Q59: Brown Company makes watches.The budgeted fixed overhead
Q60: The budgeted fixed overhead rate per output