Multiple Choice
Use the information below to answer the following question(s) .Michelle Inc.uses a level 4-variance analysis of its manufacturing overhead costs, and has the following results for April.A.Budgeted direct labour-hours per unit is used to allocate variable manufacturing overhead.Fixed overhead is allocated on a per unit basis.
b.Budgeted amounts for April are:
C.Actual amounts for April are:
-What are the fixed manufacturing overhead efficiency and production-volume variances, respectively?
A) 0; $200,000 favourable
B) 0; $200,000 unfavourable
C) $50,500 favourable; $199,998 unfavourable
D) $50,500 unfavourable; $199,998 favourable
E) There is no efficiency variance; $200,000 favourable.
Correct Answer:

Verified
Correct Answer:
Verified
Q55: The variable overhead efficiency variance can be
Q72: Using a standard costing system makes it
Q73: Use the information below to answer the
Q74: Answer the following question(s)using the information below.Willis
Q75: Which option(s)would be consistent with the proration
Q76: There is causal relationship between the variable
Q78: Use the information below to answer the
Q80: Answer the following question(s)using the information below.Rutch
Q81: Effective planning of variable overhead costs means
Q82: If budgeted machine-hours allowed per actual output