A local engineering firm is bidding on a design project for a new client.The total budgeted direct labour costs for the firm are $800,000.The total budgeted indirect costs are $1,200,000.It is estimated that there are 16,000 billable hours in total.Required:
a.What is the budgeted direct labour cost rate?
b.What is the budgeted indirect cost allocation rate assuming direct labour cost is the cost allocation base?
c.What should be the engineering firm bid on the project if the direct labour hours are estimated at 500 hours?
Correct Answer:

Verified
a.$800,000/16,000 = $50/hour
b...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
b...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q101: Use the information below to answer the
Q102: For each item below indicate the source
Q103: Use the information below to answer the
Q104: What is the appropriate journal entry if
Q105: Use the information below to answer the
Q107: In a job-costing system, explain why it
Q108: Camden Company gathered the following information for
Q109: Use the information below to answer the
Q110: Cost tracing is a specific term for
Q111: A wholesale automobile company that buys and