Multiple Choice
Quick Shop Printing has two workstations, cutting and pasting.The cutting station is limited by the speed of operating the cutting machine.Pasting is limited by the speed of the workers.Pasting normally waits on work from cutting.Each department currently works an eight-hour day.The company is considering having cutting begin work two hours earlier than pasting each day, the two departments would then finish their work at the same time.Not only does this eliminate the bottleneck, but it increases finished units produced each day by 80 units.All units produced can be sold even though the change increases inventory stock by 10 percent from 200 units.The cost of operating the cutting department two more hours each day is $800.The contribution margin of the finished products is $3 each.Inventory carrying costs are $0.20 per unit per day.What is the change in the daily contribution margin if the change is made?
A) $(396)
B) $(564)
C) $240
D) $236
E) $(604)
Correct Answer:

Verified
Correct Answer:
Verified
Q117: Two important drivers of time are limited
Q149: Answer the following question(s)using the information below.Penny's
Q150: Correctly identifying the cost driver and separating
Q151: Use the information below to answer the
Q152: Costs of quality include all of the
Q155: Use the information below to answer the
Q156: The Gangwere Company has assembled the following
Q157: Answer the following question(s)using the information below.Penny's
Q158: Time-series data analysis includes<br>A)using a variety of
Q159: Newton Company used linear regression analysis to