Multiple Choice
To complete the first setup on a new machine took an employee 200 minutes.Using an 80% cumulative average-time learning curve indicates that the second setup on the new machine is expected to take
A) 160 minutes.
B) 120 minutes.
C) 80 minutes.
D) 60 minutes.
E) 128 minutes.
Correct Answer:

Verified
Correct Answer:
Verified