Warner Manufacturing Has Established the Following Master Flexible Budget for the Current

Question 71

Essay

Warner Manufacturing has established the following master flexible budget for the current year: Warner Manufacturing has established the following master flexible budget for the current year:        Manufacturing overhead is applied on the basis of machine hours.At standard,each unit of product requires one machine hour to complete. Required: a)The denominator activity level is 120,000 units.What are the predetermined variable and fixed manufacturing overhead rates? b)Actual data for the year were as follows:
Warner Manufacturing has established the following master flexible budget for the current year:        Manufacturing overhead is applied on the basis of machine hours.At standard,each unit of product requires one machine hour to complete. Required: a)The denominator activity level is 120,000 units.What are the predetermined variable and fixed manufacturing overhead rates? b)Actual data for the year were as follows:
Manufacturing overhead is applied on the basis of machine hours.At standard,each unit of product requires one machine hour to complete.
Required:
a)The denominator activity level is 120,000 units.What are the predetermined variable and fixed manufacturing overhead rates?
b)Actual data for the year were as follows:

Correct Answer:

verifed

Verified

blured image
Compute the variable overhead spending...