Multiple Choice
Which of the following methods of project analysis are biased towards short-term projects?
I.internal rate of return
II.net present value
III.payback
IV.discounted payback
A) I and II only
B) III and IV only
C) II and III only
D) I and IV only
E) II and IV only
Correct Answer:

Verified
Correct Answer:
Verified