Multiple Choice
Which of the following statements about theoretical capacity is best?
A) Theoretical capacity allows adjustments for preventive maintenance.
B) Running a factory at its theoretical capacity for a short time is often better than permanently raising resource levels.
C) Theoretical capacity levels are usually lower than rated capacity levels.
D) Theoretical capacity levels take into account that machines occasionally break and that workers occasionally call in sick.
Correct Answer:

Verified
Correct Answer: