The Planning Technique That Uses the Master Production Schedule to Monitor

Question 59

Multiple Choice

The planning technique that uses the master production schedule to monitor key resource requirements is:


A) rough-cut capacity planning.
B) horizon planning.
C) resource planning.
D) handfield planning.

Correct Answer:

verifed

Verified