Multiple Choice
Which of these actions would tend to make an MRP system less nervous?
A) using the same component, such as a fastener, at multiple levels throughout the product structure tree
B) making the minimum order quantity as small as possible
C) increasing the number of levels in a product structure tree
D) increasing the minimum order quantities only at the highest level of a bill or materials
Correct Answer:

Verified
Correct Answer:
Verified