  5. Question
    Once a System Has Been "Leaned Out" with All Excess
Solved

Once a System Has Been "Leaned Out" with All Excess

Question 57

Question 57

Short Answer

Once a system has been "leaned out" with all excess inventory removed, if a piece of production equipment breaks, all activity on the production line ________.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q52: The just-in-time philosophy applies only to the

Q53: Two announcers are used to read names

Q54: In the water and rocks analogy for

Q55: Consider the adjacent work stations in this

Q56: An increase in the safety factor results

Q58: What are the consequences of unstable demand

Q59: Livermore Industries uses a kanban system to

Q60: Livernonions Industries uses a kanban system to

Q61: The ability of a process to produce

Q62: JIT or Lean can be used in:<br>A)repetitive

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines