Question 10

Essay

Construction of the cattery could be distilled to eight distinct steps, from the official groundbreaking ceremony to the cutting of the litterbox ribbon. The activities, their durations and predecessors are shown in the table below. Determine earliest and latest start and finish times for all of the activities.
 Activity  Predecessors  Time (weeks)  A 10 B  A 8 C  A 7 D  C 11 E  D 12 F  B 11 G  E, F 6 H  E, F 9\begin{array} { | c | c | c | } \hline \text { Activity } & \text { Predecessors } & \text { Time (weeks) } \\\hline \text { A } & \cdots & 10 \\\hline \text { B } & \text { A } & 8 \\\hline \text { C } & \text { A } & 7 \\\hline \text { D } & \text { C } & 11 \\\hline \text { E } & \text { D } & 12 \\\hline \text { F } & \text { B } & 11 \\\hline \text { G } & \text { E, F } & 6 \\\hline \text { H } & \text { E, F } & 9 \\\hline\end{array}

Correct Answer:

verifed

Verified

\[\begin{array} { | c | c | c | c | c | ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions