Solved

Haven Corp \quad \quad \quad \quad \quad

Question 59

Multiple Choice

Haven Corp. contracted to construct a building for $ 750,000. Construction began in 2020 and was completed in 2021. Data relating to the contract follow: \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad Year ended
\quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad \quad December 31 .

Costs incurred.Estimated costs to complete2020$300,000200,0002021$230,000\begin{array}{c}\begin{array}{lll}\text {Costs incurred.}\\\text {Estimated costs to complete} \end{array}\begin{array}{r} \underline{2020}\\\$ 300,000 \\200,000\end{array}\begin{array}{r} \underline{2021}\\\$ 230,000\\-\end{array}\end{array}

Haven uses the percentage-of-completion method. For the calendar years 2020 and 2021, respectively, Haven should report gross profit of


A) $ 135,000 and $ 85,000.
B) $ 450,000 and $ 300,000.
C) $ 150,000 and $ 70,000.
D) $ 0 and $ 220,000.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions