Question 98

Essay

Presentation & the percentage-of-completion method
Thuxton Inc. began work on a $ 6,000,000 non-cancellable contract in 2020 to construct a retail building. During 2020, Thuxton incurred costs of $ 1,500,000 and billed its customers for $ 1,400,000 (non-refundable), and collected $ 1,000,000. At December 31, 2020, the estimated future costs to complete the project total $ 2,500,000.
Instructions
Prepare Thuxton's 2020 journal entries using the percentage-of-completion method.