Solved

Coquel Company Has a Non-Cancellable Contract to Construct a Bridge

Question 25

Essay

Coquel Company has a non-cancellable contract to construct a bridge for an estimated cost of $ 1,950,000. The contract is to start in July 2020, and the bridge is to be completed in September 2022. The following data pertain to the construction period. Assume that progress billings are non-refundable.
Costs to dateEstimated costs to completeProgress billings during theyearCash collected during the year2020$360,0001,260,000305,00280.0002021$900,000380,000765,000760.0002022$390,0001,200,0002,000,000\begin{array}{c}\begin{array}{lll}\\\text {Costs to date}\\\text {Estimated costs to complete}\\\text {Progress billings during theyear}\\\text {Cash collected during the year}\end{array}\begin{array}{r}2020\\\hline\$ 360,000 \\1,260,000 \\305,00\\280.000\end{array}\begin{array}{r}2021\\\hline \$ 900,000 \\380,000\\765,000\\760.000\end{array}\begin{array}{r}2022\\\hline\$ 390,000\\-\\ 1,200,000 \\ 2,000,000 \end{array}\end{array}
Instructions
Assuming that Coquel Company uses the percentage of completion method prepare the appropriate journal entries.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions