Multiple Choice
Cedar Designs Company,a custom cabinet manufacturing company,is setting standard costs for one of its products.The main material is cedar wood,sold by the square foot.The current cost of cedar wood is $6.00 per square foot from the supplier.Delivery costs are $0.25 per square foot.Carpenters' wages are $30.00 per hour.Payroll costs are $3.60 per hour,and benefits are $6.00 per hour.How much is the direct labor standard cost per hour?
A) $30.00
B) $9.60
C) $33.60
D) $39.60
Correct Answer:

Verified
Correct Answer:
Verified
Q2: A company's production department was experiencing a
Q80: What does the variable overhead cost variance
Q101: Judd Company uses standard costs for
Q102: When using management by exception,which of the
Q109: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5020/.jpg" alt=" -According to the
Q111: A company is setting its direct materials
Q142: Companies conduct time-and-motion studies and use benchmarks
Q203: The static budget is used to compute
Q214: When using management by exception,managers investigate only
Q221: Cavalaris Products uses a standard cost system.Variable