Multiple Choice
The sum of the cost variances and efficiency variances equals ________.
A) the static budget variance
B) the flexible budget variance
C) the difference between the flexible budget and the static budget
D) the difference between the static budget and the previous year's actual results
Correct Answer:

Verified
Correct Answer: