Multiple Choice
A company's production department was experiencing a high defect rate on the assembly line,which was slowing down production and causing a higher waste of valuable direct materials.The production manager decided to recruit some highly skilled production workers from another company to bring down the defect rate.This would produce a(n) ________.
A) unfavorable direct materials cost variance
B) favorable direct labor cost variance
C) favorable direct labor efficiency variance
D) unfavorable direct materials efficiency variance
Correct Answer:

Verified
Correct Answer:
Verified
Q157: An efficiency variance measures how well a
Q158: The purchasing manager was able to bring
Q159: A manufacturer,using a standard cost system,purchased 250
Q160: What does the variable overhead efficiency variance
Q161: A direct labor cost variance is unfavorable
Q163: Based on the following,what is the total
Q164: Which of the following statements about management
Q165: Managers should look at any variance that
Q166: The purchasing manager was able to bring
Q167: Golden Glow Company manufactures candles.The standard direct