Multiple Choice
Use the information below to answer the following questions:
On 1 January 2010, Romulus Ltd signed a contract worth $21 000 000 to construct a light rail from here to there. The light rail was to be built over 3 years, with progress payments of $7 000 000 to be made at the end of each year. Estimated costs were $15 000 000 and the following costs incurred and paid by Romulus Ltd were in accordance with estimates and represented the percentage completed in each year:
The project was completed in December 2012.
-Using the percentage of completion method,what profit would Romulus Ltd report in 2010?
A) $800 000
B) $2 000 000
C) $3 200 000
D) $1 300 000.
Correct Answer:

Verified
Correct Answer:
Verified
Q19: Although revenue may be recognised at various
Q36: Use the information below to answer
Q37: Use the information below to answer the
Q38: Use the information below to answer the
Q39: Use the information below to answer the
Q42: Use the information below to answer the
Q43: Identify the point at which revenue would
Q44: Use the information below to answer
Q45: Revenue should not be recognised unless:<br>A) the
Q46: Use the information below to answer the