Multiple Choice
Use the information below to answer the following questions:
On 1 January 2010, Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium. The stadium was to be built over three years, with progress payments as follows:
Estimated costs were $50 000 000. The project was 35% complete at the end of 2010, 75% complete at the end of 2011, and 100% complete at the end of 2012. Revenues and costs were as estimated.
-What profit was earned during 2012 if the percentage of completion method was used?
A) $3 500 000
B) $5 600 000
C) $6 343 750
D) $14 000 000.
Correct Answer:

Verified
Correct Answer:
Verified
Q33: Which of the following statements about the
Q47: Use the information below to answer the
Q48: Which of the following transactions should not
Q49: When services are provided,it is customary to
Q51: Use the information below to answer the
Q52: Use the information below to answer the
Q54: Use the information below to answer the
Q55: Highrise Constructions Ltd had a large 3-year
Q56: Under which of the following circumstances would
Q57: Highrise Constructions Ltd had a large 3-year