Midwest Rocks receives and produces an order.What is the company's cycle time assuming the following times were measured during production of this order?
Process time: .7 days Inspection time: .25 days Move time: 1.05 days Wait time: .5 days
A) 1.8 days
B) .7 days
C) .95 days
D) 2 days
E) 2.5 days