Solved

A Company Estimates That Overhead Costs for the Next Year

Question 95

Multiple Choice

A company estimates that overhead costs for the next year will be $9,234,000 for indirect labor and $156,800 for factory utilities.The company uses machine hours as its overhead allocation base.If 500,000 machine hours are planned for this next year,what is the company's plantwide overhead rate? (Round to two decimal places)


A) $0.05 per machine hour.
B) $18.47 per machine hour.
C) $18.78 per machine hour.
D) $0.31 per machine hour.
E) $3.19 per machine hour.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions