Multiple Choice
Juarez Builders incurred $285,000 of labor costs for construction jobs completed during the month of August,of which $212,000 was direct and $73,000 was indirect supervisory costs.The correct journal entry to record the direct labor for the month is:
A) Debit Payroll Expense $212,000; credit Cash $212,000.
B) Debit Factory Wages Payable $285,000; credit Work in Process Inventory $212,000.
C) Debit Work in Process Inventory $212,000; credit Cash $285,000.
D) Debit Work in Process Inventory $285,000; credit Factory Wages Payable $285,000.
E) Debit Work in Process Inventory $212,000; credit Factory Wages Payable $212,000.
Correct Answer:

Verified
Correct Answer:
Verified
Q9: Adams Manufacturing allocates overhead to production on
Q67: _, or customized production, produces products in
Q118: The following information about the Zhang Company
Q119: The balance in the Work in Process
Q121: Job order costing applies to manufacturing firms
Q123: Minstrel Manufacturing uses a job order costing
Q125: Requisitions of indirect materials are not recorded
Q126: Portside Watercraft uses a job order costing
Q149: Labor costs in production can be:<br>A) Direct
Q177: Predetermined overhead rates are calculated at the