Consider the Following PERT/CPM Network with Estimated Times in Weeks

Question 35

Essay

Consider the following PERT/CPM network with estimated times in weeks.The project is scheduled to begin on May 1. Consider the following PERT/CPM network with estimated times in weeks.The project is scheduled to begin on May 1.   The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:     a.Give the expected project completion date and the critical path. b.By what date are you 99% sure the project will be completed? The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:
Consider the following PERT/CPM network with estimated times in weeks.The project is scheduled to begin on May 1.   The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:     a.Give the expected project completion date and the critical path. b.By what date are you 99% sure the project will be completed?
a.Give the expected project completion date and the critical path.
b.By what date are you 99% sure the project will be completed?

Correct Answer:

verifed

Verified

a.16 weeks = Aug.21b...