Essay
Consider the following PERT/CPM network with estimated times in weeks.The project is scheduled to begin on May 1. The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity:
a.Give the expected project completion date and the critical path.
b.By what date are you 99% sure the project will be completed?
Correct Answer:

Verified
a.16 weeks = Aug.21b...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q11: A critical activity can be part of
Q13: When activity times are uncertain,an activity's most
Q23: The earliest finish time for the final
Q24: The earliest start time for an activity
Q39: Activities G,P,and R are the immediate predecessors
Q40: Which of the following is always true
Q49: The length of time an activity can
Q51: Activities K,M,and S immediately follow activity H,and
Q56: Which of the following is a general
Q57: Crashing refers to an unanticipated delay in