Consider a project that has been modeled as follows:
a.Draw the PERT/CPM network for this project and determine project's expected completion time and its critical path.
b.Can activities E and G be performed simultaneously without delaying the minimum project completion time?
c.Can one person perform A,G,and I without delaying the project?
d.By how much can activities G and L be delayed without delaying the entire project?
e.How much would the project be delayed if activity G was delayed by 7 hours and activity L was delayed by 4 hours? Explain.
Correct Answer:

Verified
a.
Expected Completion Time = 58;Crit...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
Expected Completion Time = 58;Crit...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q8: Activities following a node<br>A) can begin as
Q9: All activities on a critical path have
Q11: When activity times are uncertain, total project
Q28: Arcs in a project network indicate<br>A)completion times.<br>B)precedence
Q31: For an activity with more than one
Q34: In deciding which activities to crash, one
Q37: The latest finish time for an activity
Q38: The variance in the project completion time
Q50: It is possible to have more than
Q57: The critical path<br>A) is any path that