True/False
The latest finish of an activity is the earliest late start of any immediately preceding activity
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q17: The expected duration of this project is:<br>A)12<br>B)17<br>C)20<br>D)36<br>E)77
Q77: What is the estimated mean time for
Q78: A common assumption when using PERT/Cost is
Q80: When making a backward pass through a
Q81: What is the estimated slack time for
Q82: The earliest start of an activity is
Q83: <br>-What is the estimated mean time
Q84: In PERT,the project duration will never exceed
Q85: <br>-What is the estimated mean time
Q86: The path with the greatest slack is:<br>A)A-E