Multiple Choice
The earliest start time for an activity is:
A) based on the length of the critical path
B) determined by the maximum of the earliest finish times of its immediate predecessors
C) determined by the maximum of the earliest finish times of its immediate successors
D) the same as the latest start time of its immediate predecessor
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q82: The earliest start of an activity is
Q83: <br>-What is the estimated mean time
Q84: In PERT,the project duration will never exceed
Q85: <br>-What is the estimated mean time
Q86: The path with the greatest slack is:<br>A)A-E
Q87: The critical path is:<br>A)A-E <br>B)B-F <br>C)C-D-F <br>D)C-G
Q88: The length of the critical path is
Q89: The mean critical path is the path
Q91: <br>-What is the estimated mean time
Q92: A normal distribution is usually used to