menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Introduction to Management Science
  4. Exam
    Exam 16: Pert CPM models for project management
  5. Question
    In a Project Network the Critical Path Is the Sequence
Solved

In a Project Network the Critical Path Is the Sequence

Question 20

Question 20

Multiple Choice

In a project network the critical path is the sequence of activities which has:


A) the most activities
B) the fewest activities
C) the most events
D) the longest time
E) the greatest variance

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q17: In an Activity-On-Node project network,the nodes are

Q18: Project managers must often function in an

Q21: Which of the following are ways of

Q22: The latest starting time for an activity

Q23: Activity C in a project network has

Q24: The path with the greatest slack is:<br>A)A-E-H

Q25: <br>-What is the estimated mean time

Q71: The earliest finish time for an activity

Q71: What is the estimated standard deviation in

Q88: Activity C has an early start time

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines