Multiple Choice
Which of the following is not a feature of PERT/CPM?
A) An estimate of how long a project will take
B) A graphical display of project activities
C) An indication of crucial activities
D) An indication of slack time
E) All are features
Correct Answer:

Verified
Correct Answer:
Verified