    The Slack for Path A-D-H-I Is
Solved

The Slack for Path A-D-H-I Is

Question 59

Question 59

Multiple Choice

The slack for path A-D-H-I is:


A) 0
B) 3
C) 4
D) 7
E) 8

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q54: <br>-What is the estimated standard deviation

Q55: Projects involve routine activities that are performed

Q56: A Gantt chart of a project shows

Q57: The sum of durations of the longest

Q58: PERT/Cost is a systematic procedure to help

Q60: A manager has decided that an activity

Q61: An immediate predecessor of an activity must

Q62: If an activity is not on the

Q63: When calculating the probability that a project

Q64: The path in a project network with

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines