Multiple Choice
There are four activities on the critical path,and they have standard deviations of 1,2,4,and 2 days The standard deviation of the critical path is:
A) 3 days
B) 5 days
C) 9 days
D) 16 days
E) 25 days
Correct Answer:

Verified
Correct Answer:
Verified