Multiple Choice
There are four activities on the critical path Coincidentally,their standard deviations are all equal to 4 The standard deviation of the critical path is therefore equal to:
A) 2 days
B) 4 days
C) 8 days
D) 16 days
E) 64 days
Correct Answer:

Verified
Correct Answer:
Verified