Multiple Choice
What is the estimated standard deviation in the time for activity E?
A) 2 days
B) 3 days
C) 4 days
D) 16 days
E) 24 days
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q36: Slack time is equal to LS-ES or
Q53: The probability that the project will go
Q63: Most likely time generally is more than
Q74: The project management strategy of injecting additional
Q81: If two consecutive activities on the same
Q92: The expected duration of this project is:<br>A)13<br>B)15<br>C)20<br>D)52<br>E)81
Q93: In crashing this project to 18 weeks,
Q95: The critical path for the network shown
Q97: If an activity is determined to be
Q98: In PERT, the path with the fewest