Multiple Choice
Which of the following are advantages of computer simulation over analytical methods like PERT/CPM for predicting the probability that a project will complete by a deadline?
A) It does not need to make as many simplifying assumptions
B) It is more flexible about which probability distributions can be used
C) It provides a solution more quickly
D) All of the above
E) a and b only
Correct Answer:

Verified
Correct Answer:
Verified