Multiple Choice
A project development team at Midwest Construction was assigned the task of improving the efficiency of the firm's accounting information system.As part of the ______ step in systems development life cycle,the team has initiated an end user training program in preparation for switching over to the new system.
A) systems analysis
B) operations and maintenance
C) implementation and conversion
D) physical design
E) conceptual design
Correct Answer:

Verified