Multiple Choice
Which of the following is the last step in developing an activity-based costing system?
A) estimating the total quantity of the cost driver
B) estimating the total indirect costs of each activity
C) identifying the activities
D) allocating costs to the cost object
Correct Answer:

Verified
Correct Answer:
Verified