A job was budgeted to require 3 hours of labor per unit at $8.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $198,000.
-What is the direct labor rate variance?


A) $16,000 unfavorable.
B) $22,000 unfavorable.
C) $6,000 unfavorable.
D) $22,000 favorable.
E) $16,000 favorable.