Multiple Choice
Ship Co. produces storage crates that require 1.2 meters of material at $.85 per meter and 0.1 direct labor hours at $15.00 per hour. Overhead is applied at the rate of $9 per direct labor hour. What is the total standard cost for one unit of product that would appear on a standard cost card?
A) $2.40.
B) $3.42.
C) $11.52.
D) $25.02.
E) $2.52.
Correct Answer:

Verified